Hydroelectric Dam

Hydroelectric Dam

Market

Power

Challenge

A newly constructed hydroelectric dam with three water turbines had several issues with welds on the auxiliary cooling water and lube oil lines.

Epoxy coating sections of a pipe

Engineered Solution

The general contractor decided against rewelding all of the defective welds and instead decided to reinforce these welds using HydraWrap®,a carbon fiber reinforcement system.

Scope

All defective welds were identified and the substrate abraded. Once the substrate was prepared, the HydraWrap® system was installed. The HydraWrap® system consisted of a two-part epoxy system of primer (substrate), wet out epoxy (fabric), and carbon fabric.

HydraWrapped sections of pipes

Solution

The entire project consisted of reinforcing nearly 1000 welds. The project was completed with a small crew in a confined space with a duration of six weeks. This process saved the client more than 75% in cost and time compared to traditional repairs.

HydraWrapped sections of pipes